Cool Spring Annex-Judy Hoyer
Cool Spring Annex-Judy Hoyer
Status Design |
Funding Model Staged Renovation |
Project Type Replacement |
Budget $90,000,000 |
Architect Gilbert Architects |
General Contractor TBD |
Project Manager Joseph Howell |
School Information
Principal Laura Carr-Degen |
Address 8910 Riggs Road, Adelphi, MD 20783 |
Neighborhood Adelphi |
School Board District District 3 |
County Council District District 2 |
State Legislative District District 47 |
Project Timeline
![](/globalassets/offices/capital-programs/images/project-timelines/cool-spring-timeline.png)
Project Scope
Phase I
Construction of a new school in front of the existing Cool Spring Elementary School while the existing school is in operation. The proposed school, including the Judy Center is anticipated to be three floors and accommodate 900 students. The new school will be built to be energy efficient and meet all current building and accessibility codes.
Phase II
After completion of the new school, the school portion of the existing building will be demolished and a new building will be constructed consisting of a Therapy Pool, Central Administration spaces for ESOL, International Admissions, Bilingual, and Translation services as well as the community program for Family Support Center.
Phase III
Staff for the Phase II spaces will move in. Afterward the old convent building will be demolished and final sitework will be completed including site access and playfield improvements.
News & Announcements
There are currently no announcements for this project.
Project Updates
Past Month's Accomplishments
- A Request for Proposals was sent to perspective construction management firms to procure a general contractor for the project. Bids were due by December 17, 2024.
- Multiple construction management proposals were received.
January Lookahead
- A construction manager will be selected between the end of January and the beginning of February.
- PGCPS and the project design team response to Maryland State Department of Education design development comments are ongoing.
- Educational specifications for Phase 2 of the project will be submitted.
Past Month's Accomplishments
- The planning process continued with input from the curriculum administrators.
September Lookahead
- The Design Development package will be finalized and submitted.
- The Request for Proposal for a construction manager will be finalized and released.
Past Month's Accomplishments
- Permitting and planning are ongoing.
- PGCPS provided responses to the review comments by the IAC on June 21, 2024.
- The RFP for procurement of Construction Management Services was finalized to be put out for bidding.
July Lookahead
- The RFP will be put out for bidding.
- A construction manager will be obtained.
Past Month's Accomplishments
- Educational specifications were approved by the Board on January 11, 2024, and are currently under review by the State.
- Feasibility Study is completed and approved by the Board.
- The Schematic Design phase confirming the project's areas, physical requirements, square footage, total project budget, and schedule was completed and is under review by the State.
- A Request for Proposals for professional construction manager (CM) services was developed and sent out for responses.
May Lookahead
- The Design Development phase will continue.
- Meetings with PGCPS, IAC, and school leadership will continue.
- Construction Manager Services to be bid and awarded.
Past Month's Accomplishments
- The feasibility study and educational specifications have been approved by the Board of Education.
February Lookahead
- The guaranteed maximum price contract will be finalized to obtain construction management services.
Past Month's Accomplishments
- The Feasibility study is completed and submitted for BOE approval at the October Board Meeting.
Next Month's Lookahead
- Educational Specifications will be completed.
- Schematic design will continue.
- Meetings with PGCPS and School Leadership will occur.