Central High School HVAC Renovation
Central High School HVAC Renovation
Scope of Work
Systemic Renovation: Replace the entire 1982 heating and ventilating system with a complete heating, ventilating and air conditioning system, including boilers, chiller, rooftop units, air handling units, terminal units, piping, and controls.
Project Details
- Budget: $20,218,000
- Planning/Design Start: 2016
- Construction Start: March 2020
- Phase & Percentage Complete: Construction; 95%
- Current Status: Substantial completion achieved- school in function.
- Upcoming Activities: Final close out items in progress: final inspections and training.
- Project Team:
- PGCPS Contact: Anoop Gupta, Project Manager