Dwight Eisenhower Middle School HVAC Renovation
Dwight Eisenhower Middle School HVAC Renovation
Scope of Work
Systemic Renovation: HVAC & Building Envelope / Replace the 1969-1974 central controls system, HVAC piping, all ten (10) AHUs, 45 finned tube radiators, four (4) self-contained unit ventilators, 17 floor mounted fan coil units, two (2) ceiling mounted AHUs, chiller
Project Details
- Budget: $12,063,600
- Planning/Design Start: 2017
- Construction Start: June 2021
- Phase & Percentage Complete: Construction; 49%
- Current Status: In construction.
- Upcoming Activities: Punchlist/corrective items.
- Project Team:
- PGCPS Contact: Anoop Gupta, Project Manager